Here is the plan for City Hall. Note that NO NEW departments will be added. The addition part will be a grand two story council chambers with an impressive two story lobby, private hallways and private bathroom for council.
The original cost to restore and rehab the 1926 portion and to replace the 1979 section was to be $4,120,000. This amount has ballooned to at least $15,887,210 plus costs for excluded items as of April 2024.
This amount does not include all the work that needs to be done such as FPL Solar Now relocation, ADA parking on Harvey St, Fixtures, Furniture, Equipment, buildout of interior office space, site work, and W Marion Ave street drainage. .